Tiny House Update #2

Tiny House Update #2

Over the last week, lots of work was done on the Tiny House! Volunteers poured footings and did lots of shoveling! We hope to fill in the middle and build more forms so the slab can be poured on Thursday! Check out the week in pictures below! The work continues! As...
Tiny House Update #1

Tiny House Update #1

We’re well on the way! Perry staked out the lot on Wednesday, 10/28, with the help of Phil and Dannie. After receiving city approval to start digging, the work began on Saturday morning, 10/31! Lot as it looked at the end of the day Saturday.  Three sides of...
Groundbreaking Blessing

Groundbreaking Blessing

On Monday, October 26, about twenty-five of us, including representatives from CU at Home and the city of Champaign, met on-site at 509 Alabama Ave to pray a blessing over the work. These are the words we shared: Welcome to 509 Alabama Avenue, the future location of a...